- Visit opened
- 1 Oct, 10:14 WAT · 1 Oct, 04:14 CDT
- Record closed
- 10:29 WAT · 04:29 CDT
- Requested by
- The owner (Dallas)
- Captured by
- Site supervisor, invited by the owner
1Summary
EV-01 · Vantage point 1 (front)- Captured by
- Site supervisor, invited by the owner
- Visit opened
- 10:14 WAT · 04:14 CDT
- Record closed
- 10:29 WAT · 04:29 CDT
- Captures
- 8 (7 photos, 1 video)
- Site coverage
- Completeestimated
- Location
- 2 inside, 6 likely insidePhone GPS, accurate to a few metres; each capture shows its own reading.
- Timing
- All captured during the visit; 2 captures taken without signal and received later
- Integrity
- No inconsistency detected
- Visit continuity
- With interruptions: 2 captures taken without signal, received later
- Milestone
- Lintel to roof (automated estimate)
2Visit timeline
Property time (WAT) first, the owner's time (CDT) alongside. Each capture shows when it was taken and when NEMZIO received it.
- 1 Oct, 03:05 WAT · 30 Sep, 21:05 CDTRequest sent by the owner“The contractor says roofing has started. Please show me the roof.”
- 10:14 WAT · 04:14 CDTVisit openedAt the gate: likely inside (4 m from the boundary, GPS ±6 m)
- 10:16 WAT · 04:16 CDTEV-01First capture
- 10:22 WAT · 04:22 CDTEV-05, EV-06No signal: 2 captures held on the phone
- 10:25 WAT · 04:25 CDTEV-05, EV-06Signal back: the held captures were received
- 10:28 WAT · 04:28 CDTEV-08Last capture
- 10:29 WAT · 04:29 CDTFinished on the phone
- 10:29 WAT · 04:29 CDTRecord closed: all 8 captures received
- 10:30 WAT · 04:30 CDTChecks finishedChecks passed · claim not supported
3Coverage
Complete Every side in view. Estimated from where each view was taken and which way it faced.
All 4 reference views were captured, so this visit compares side by side with the previous one (SW-G8EQ-TT9J-VGGY). 8 captures in total: 7 photos and 1 video, 4 of them added for this visit.
4Claim vs evidence
Automated comparison of what the owner was told with what this visit shows. Not a professional opinion; NEMZIO never advises on payments.
“Roofing has started. The roof timbers are up.”
Contractor · WhatsApp message, 29 Sep
None of this visit's 7 views of the walls and the roof line show roof timbers or sheets, so this visit doesn't show roofing having started.
- Roof line from the back and the front (EV-06, EV-08): wall tops open, nothing fixed on top
- Reference views of all 4 sides (EV-01, EV-04, EV-05, EV-07): walls at roof level; no roof timbers or sheets
- Roof timbers, trusses or sheets on any side
5What changed
Since the previous visit on 17 Sep 2026, from comparable reference views. Automated observations, labelled as such.
- Walls raised from lintel level to roof level on every side
- Front gable formed
- Walls rendered
- Arched openings formed, with metal grilles
- Timber scaffolding along the front and the left side
- 12 bags of cement stacked by the gate on 17 SepThe spot by the gate is clear in today's view (EV-03).
Not visible is not the same as gone: the cement may have been used in the walls raised since, or moved somewhere this visit didn't look. Ask the person on site.
MilestoneBlockwork to lintel → Lintel to roof (Automated estimate from the photos: a milestone, not a measured percentage.)
6Evidence
Every capture with its own time and location result. Drawings stand in where the sample has no matching photo, and say so.
EV-01Front: walls at roof level, rendered, front gable formed, arched openings with metal grilles, timber scaffolding along the front. No roof timbers or sheets.
- Captured
- 10:16 WAT
- Received
- 10:16 WAT
6-second clip, turning from the front towards the right side: walls at roof level, no roof timbers or sheets.
- Captured
- 10:16 WAT
- Received
- 10:17 WAT
The gate and the road in front. The spot by the gate is clear.
- Captured
- 10:18 WAT
- Received
- 10:18 WAT
Left side: walls at roof level, rendered, arched openings with metal grilles, timber scaffolding along the left side. No roof timbers or sheets.
- Captured
- 10:20 WAT
- Received
- 10:20 WAT
Back: walls at roof level, rendered, arched openings with metal grilles. No roof timbers or sheets.
- Captured
- 10:22 WAT · no signal
- Received
- 10:25 WAT
Roof line from the back: wall tops open, nothing fixed on top. No roof timbers or sheets.
- Captured
- 10:24 WAT · no signal
- Received
- 10:25 WAT
Right side: walls at roof level, rendered, arched openings with metal grilles. No roof timbers or sheets.
- Captured
- 10:26 WAT
- Received
- 10:26 WAT
Roof line from the front: wall tops open, nothing fixed on top. No roof timbers or sheets.
- Captured
- 10:28 WAT
- Received
- 10:28 WAT
7Limits
- Where and when each capture was made, with the precision of the reading
- Which sides of the property the visit likely had in view, and which it didn't
- When each capture was taken during the visit, and when it reached NEMZIO
- What changed between visits, from comparable views (construction, paid plans)
- Whether the stored record has changed since it was shared
- Legal title or ownership of land or a building
- Survey-grade location or boundaries (phone location can be off by several metres)
- That a structure is safe, sound or built to code
- Compliance with planning, building or other regulations
- That a contractor or anyone else is honest, or that work was paid for or authorised
- That a payment should be made or was authorised
- That manipulation is impossible: NEMZIO's checks make it hard and say when something doesn't add up, but no system can rule it out entirely